Kachess Community Association et al v. US Department of the Interior et al, No. 1:2019cv03155 - Document 43 (E.D. Wash. 2020)

Court Description: ORDER GRANTING DEFENDANTS' MOTION TO DISMISS; granting 22 Defendants Washington State Department of Ecology and its former Director Maia Bellon's Motion to Dismiss State Law Claims; granting 23 Intervenor Roza Irrigation District's Motion to Dismiss; granting 25 Defendants United States Department of the Interior, Bureau of Reclamation and its Commissioner Brenda Burman's Motion to Dismiss. Plaintiffs' claims are DISMISSED WITHOUT PREJUDICE, without costs or fees for any party and WITHOUT LEAVE TO AMEND. Judgment of Dismissal is entered without prejudice. Case is closed. Signed by Judge Rosanna Malouf Peterson. (AY, Case Administrator)

Download PDF
Kachess Community Association et al v. US Department of the Interior et al Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 Doc. 43 PageID.985 Page 1 of 25 1 FILED IN THE U.S. DISTRICT COURT EASTERN DISTRICT OF WASHINGTON 2 Jun 26, 2020 3 SEAN F. MCAVOY, CLERK 4 5 UNITED STATES DISTRICT COURT EASTERN DISTRICT OF WASHINGTON 6 7 8 9 KACHESS COMMUNITY ASSOCIATION, a Washington nonprofit corporation; and WISE USE MOVEMENT, a Washington nonprofit corporation, 10 11 12 13 14 15 16 17 18 Plaintiffs, NO: 1:19-CV-3155-RMP ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS v. US DEPARTMENT OF INTERIOR, Bureau of Reclamation; WASHINGTON STATE DEPARTMENT OF ECOLOGY; BRENDA BURMAN, Commissioner; and MAIA BELLON, Director; and ROZA IRRIGATION DISTRICT, Intervenor Defendant, Defendants. BEFORE THE COURT are Motions to Dismiss from: (1) the Washington 19 State Department of Ecology (“Ecology”) and its former Director Maia Bellon 20 (collectively, the “State Defendants”) ECF No. 22; (2) Intervenor Roza Irrigation 21 District’s (“Roza”) ECF No. 23; and (3) the United States Department of the ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 1 Dockets.Justia.com Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.986 Page 2 of 25 1 Interior, Bureau of Reclamation (“Reclamation”) and its Commissioner Brenda 2 Burman (collectively, the “Federal Defendants”) ECF No. 25. Having reviewed the 3 Complaint, ECF No. 1; the parties’ submissions related to the Motions to Dismiss; 4 the amici curiae brief of Yakima Basin Joint Board and Trout Unlimited, ECF No. 5 30; the remaining record; and the relevant law, the Court is fully informed. 6 BACKGROUND 7 The Court recites the following factual context from the Complaint and 8 materials referenced in the Complaint. 1 9 Plaintiff Kachess Community Association is comprised of approximately 167 10 owners of property adjacent to the Lake Kachess Reservoir. ECF No. 1 at 5. 11 Plaintiff Wise Use Movement is a conservation nonprofit. Id. 12 13 In 1905, Congress authorized the development of irrigation facilities in the Yakima River basin in Washington State through the Yakima Project. ECF No. 23- 14 15 16 17 18 19 20 21 On a motion to dismiss, a district court may “consider materials incorporated into the complaint or matters of public record.” Coto Settlement v. Eisenberg, 593 F.3d 1031, 1038 (9th Cir. 2010). The Court notes that Plaintiffs ask the Court to strike an exhibit submitted by Intervenor Roza in support of its Motion to Dismiss on the basis that the Complaint did not refer to the document, or, in the alternative, asks the Court to convert Intervenor’s Motion to Dismiss into a Motion for Summary Judgment to allow Plaintiffs an opportunity to fully respond to the exhibit. ECF Nos. 32 at 32 (Plaintiffs’ Response); 23-5 (October 31, 2018 Memorandum submitted by Intervenor). The Court denies as moot Plaintiffs’ request on the basis that the Court did not consider the exhibit in rendering its decision. 1 ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 2 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.987 Page 3 of 25 1 2 at 46. In approximately the first fifty years of the Yakima Project, Reclamation 2 constructed several river diversions, in the form of canals and dams, that formed five 3 large reservoirs: Lake Keechelus, Lake Kachess, Lake Cle Elum, Bumping Lake, 4 and Rimrock Lake. Id.; see also ECF No. 23-2 at 46. 5 Reclamation manages the Yakima Project to supply water for irrigation and 6 for flood control, power generation, and instream flow for fish, wildlife, and 7 recreation. ECF No. 23-2 at 50. Reclamation annually estimates the total water 8 supply available and allocates the water among users based on the priority of their 9 water rights. Id. at 51. Non-proratable water rights holders, generally those whose 10 water rights pre-date the Yakima Project, receive their full water supply before 11 junior and proratable rights holders. ECF No. 23-3 at 19. 12 Integrated Plan 13 Beginning in approximately 2009, federal, state, and local agencies, the 14 Confederated Tribes and Bands of the Yakama Nation, Intervenor Roza, and other 15 stakeholders convened as a workgroup that developed the Yakima Basin Integrated 16 Water Resource Management Plan (“Integrated Plan”), which purports to embody a 17 “comprehensive approach to water resources and ecosystem restoration 18 improvements in the Yakima River basin.” ECF No. 25-1 at 7; see also ECF No. 19 23-2 at 67; 1 at 18. Plaintiffs allege that this workgroup, the Yakima River Basin 20 Water Enhancement Project Workgroup (“Yakima Workgroup”), “was not created 21 nor chartered under the FACA” when it formed in 2009. ECF No. 1 at 17. Plaintiffs ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 3 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.988 Page 4 of 25 1 further allege that “residents around Keechelus, Kachess, Cle Elum and Bumping 2 Lakes were excluded by Defendants from the Yakima Workgroup.” Id. at 18. 3 The Final Programmatic Environmental Impact Statement (“FPEIS”) for the 4 Integrated Plan was issued on March 2, 2012. ECF No. 25-1. The FPEIS analyzed 5 both the Integrated Plan and the alternative of “no action.” Id.; 1 at 19. The FPEIS 6 described the Integrated Plan as “intended to meet the need to restore ecological 7 functions in the Yakima River system and to provide more reliable and sustainable 8 water resources for the health of the riverine environment and for agriculture and 9 municipal and domestic needs.” ECF No. 23-2 at 9. In addition, “the Integrated 10 Plan is . . . intended to provide the flexibility and adaptability to address potential 11 climate changes and other factors that may affect the basin’s water resources in the 12 future.” Id. 13 Plaintiffs allege that the “Yakima Workgroup adopted the 2012 Yakima Plan” 14 and shifted to “implementation mode” after the FPEIS was issued. ECF No. 1 at 18. 15 This shift allegedly was manifested by formation of an “Implementation 16 Committee,” headed by Ecology and including Roza and the Washington 17 Department of Fish and Wildlife, whose “function is largely to lobby elected 18 officials” and whose meetings allegedly were “closed to the public even though two 19 state agencies are members paid for with taxpayer money.” Id. 20 21 Kachess Community Association’s members submitted comments on the FPEIS. ECF No. 1 at 6. Plaintiffs allege that, within a month after the FPEIS was ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 4 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.989 Page 5 of 25 1 issued, “fifteen local, state and national organizations wrote to Defendants with 2 FPEIS objections,” but Plaintiffs did not receive a response. ECF No. 1 at 19. Reclamation issued a Record of Decision (“ROD”) on July 9, 2013, which 3 4 selected the Integrated Plan as identified in the FPEIS to provide the framework for 5 Reclamation to work with Ecology and other federal state, local, and tribal partners 6 to manage the water resources in the Yakima River basin. ECF Nos. 1 at 10; 25-2 at 7 5. 8 9 The Integrated Plan consists of seven elements: (1) reservoir fish passage; (2) structural and operational changes to existing facilities; (3) surface water storage; (4) 10 groundwater storage; (5) habitat/watershed protection and enhancement; (6) 11 enhanced water conservation; and (7) water market reallocation. ECF No. 25-2 at 12 5−6. 13 On March 12, 2019, Congress enacted Pub. L. No. 116-9, Sections 8201- 14 8204, of the John Dingell Jr. Conservation, Management, and Recreation Act, Title 15 VIII, Subtitle C, YRBWEP Phase III (the “Dingell Act”), requiring Reclamation to 16 use the Integrated Plan to identify and implement site-specific projects. 133 Stat. 17 580, 810−21 (2019). 18 The surface water storage component of the Integrated Plan involves four site- 19 specific projects: (1) the Wymer Dam and Pump Station; (2) the Kachess Reservoir 20 Inactive Storage; (3) the Bumping Lake Reservoir Enlargement; and (4) a study of 21 Columbia River pump exchange with Yakima Storage. ECF No. 1 at 10; 23-2 at ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 5 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.990 Page 6 of 25 1 9−10. Plaintiffs allege that the fourth project, the Columbia River pump exchange, 2 is “conditioned upon later failure” of the first three projects and represents “ political 3 acceptance of the Yakima Plan by the Yakima Workgroup . . . .” ECF No. 1 at 10. 4 Each site-specific project must undergo its own environmental review under 5 the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321 et seq., and the 6 State Environmental Policy Act (“SEPA”), chapter 43.21C of the Revised Code of 7 Washington (“RCW”), before it can be approved and implemented by Reclamation 8 and Ecology. See ECF No. 1 at 11, 19 (“The course of action proposed by this 9 ‘programmatic’ EIS is to leave precise actions related to the Yakima Plan within the 10 selected ‘combination’ to be considered in later environmental compliance.”). Plaintiffs allege that the FPEIS is inadequate because it does not include an 11 12 adequate range of alternatives and, consequently, “the subsequent tiered project- 13 specific EISs that rely on it are fatally flawed.” ECF No. 32 at 2. According to the 14 Complaint, “[b]y focusing on a single action alternative comprised of distinct 15 components, the PEIS eliminates possible future alternatives from later 16 environmental review and consideration and instead ‘snowballs’ the Yakima Plan by 17 foreclosing other, viable alternatives such as aggressive water conservation, water 18 efficiencies, and water banking all of which have been proven to be effective tools to 19 conserve and manage water.” ECF No. 1 at 11. 20 / / / 21 / / / ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 6 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.991 Page 7 of 25 1 Pumping Plant 2 One tiered project that Reclamation and Ecology proposed in order to 3 effectuate the goals of the Integrated Plan involved construction of the Kachess 4 Drought Relief Pumping Plant (“KDRPP”) and the Keechelus-to-Kachess 5 Conveyance (“KKC”). Reclamation and Ecology released the Draft Environmental 6 Impact Statement (“DEIS”) for these projects in January 2015, which analyzed 7 environmental impact of the no action approach alongside five action alternatives. 8 ECF No. 23-3 at 5. The KDRPP would deliver up to an additional 200,000 acre-feet 9 of water from the inactive storage, meaning water below the current outlet channel, 10 in Lake Kachess Reservoir during times of drought. Id. at 7. 11 Plaintiffs allege in the Complaint that the 2015 DEIS is flawed because it is 12 unclear and ambiguous in several respects; it inadequately disclosed and analyzed 13 appropriate alternatives; and it did not adequately address threatened and endangered 14 species. ECF No. 1 at 19−20. 15 After the public comment period, Reclamation and Ecology “reviewed all 16 comments on the DEIS, developed a new floating pumping plant alternative, 17 collected additional scientific data as necessary, and evaluated new findings” and 18 documented those findings in a Supplemental Draft Environmental Impact 19 Statement (“SDEIS”) released to the public on April 13, 2018. ECF No. 1 at 20. 20 Plaintiffs allege that the SDEIS is flawed in that it is “extremely long,” confusing, 21 and did not disclose the need for publishing the SDEIS. Id. at 21. ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 7 Case 1:19-cv-03155-RMP 1 ECF No. 43 filed 06/26/20 PageID.992 Page 8 of 25 Reclamation and Ecology issued a final Tier-1 EIS in March 2019 (“Tier-1 2 EIS”). ECF No. 1 at 22. In April 2019, Reclamation issued a ROD (the “Tier-1 3 ROD”), determining 4 that “the remaining alternatives in the Tier-1 EIS, including the KKC, will not be 5 carried forward into the Tier-2 EIS.” ECF No. 25-4 at 4. Therefore, the Tier-1 ROD 6 determined that only the KDRPP is appropriate for further site-specific analysis in a 7 future Tier-2 EIS. ECF No. 1 at 23. 8 9 10 11 12 13 14 15 16 17 18 19 20 In their Complaint, Plaintiffs seek a declaration from the Court that: • the FPEIS and the 2013 ROD violate the procedural and substantive requirements of NEPA and SEPA; • the Kachess DEIS, Kachess SEIS, the Tier-1 EIS and the Tier-1 ROD violate the procedural and substantive requirements of NEPA and SEPA; • Defendants acted arbitrarily and capriciously in concluding the environmental documents (i.e., EISs and RODs) satisfy the procedural and substantive requirements of NEPA and SEPA; • The FPEIS, 2013 ROD, Kachess DEIS, Kachess SEIS and the Tier-1 EIS and Tier-1 ROD are inadequate under the rule of reason; • Any and all decisions and actions based on the FPEIS, 2013 ROD, Kachess DEIS, Kachess SDEIS, and the Tier-1 EIS and Tier-1 ROD are null and void; • Defendants violated the Endangered Species Act (“ESA”), 16 U.S.C. § 1531 et seq.; • Defendants violated the Federal Advisory Committee Act (“FACA”), 5 U.S.C. app. 1, § 1 et seq.; • Defendants violated the state Open Public Meetings Act (“OPMA”). 21 ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 8 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.993 Page 9 of 25 1 ECF No. 1 at 31. Plaintiffs also seek injunctive relief prohibiting Defendants 2 from further pursuing the Integrated Plan and the KDRPP. See ECF No. 1 at 3 4, 32. 4 RULE 12(b) STANDARDS 5 Fed. R. Civ. P. 12(b)(1) 6 “‘Federal courts are courts of limited jurisdiction,’ possessing ‘only that 7 power authorized by Constitution and statute.’” Gunn v. Minton, 568 U.S. 251, 256 8 (2013) (quoting Kokkonen v. Guardian Life Ins. Co. of America, 511 U.S. 375, 377 9 (1994)). A court will dismiss a complaint under Fed. R. Civ. P. 12(b)(1) upon 10 finding that the court lacks jurisdiction over the subject matter of the suit. Standing 11 is an essential aspect of the constitutional limitation that federal-court jurisdiction 12 extends only to actual cases or controversies. Simon v. E. Kentucky Welfare Rights 13 Org., 426 U.S. 26, 37 (1976). 14 “The party invoking federal jurisdiction bears the burden of establishing 15 standing.” Susan B. Anthony List v. Driehaus, 573 U.S. 149, 158 (2014) (internal 16 quotation omitted). Further, when facing a motion to dismiss under Rule 12(b)(1), a 17 plaintiff “must clearly . . . allege facts demonstrating each element.” Spokeo, Inc. v. 18 Robins, 136 S. Ct. 1540, 1547 (2016) (internal quotation omitted). Courts must 19 presume that they “lack jurisdiction unless the contrary appears affirmatively from 20 the record.” Renne v. Geary, 501 U.S. 312, 315 (1991). However, a court also 21 presumes that the plaintiff’s allegations in the complaint are true and construes the ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 9 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.994 Page 10 of 25 1 complaint in favor of plaintiff. See Levine v. Vilsack, 587 F.3d 986, 991 (9th Cir. 2 2009). 3 Fed. R. Civ. P. 12(b)(6) 4 To survive a motion to dismiss for failure to state a claim upon which relief 5 can be granted under Fed. R. Civ. P. 12(b)(6), a complaint must contain “sufficient 6 factual matter, accepted as true, to ‘state a claim to relief that is plausible on its 7 face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. 8 Twombly, 550 U.S. 544, 570 (2007)). A claim is plausible when the plaintiff pleads 9 “factual content that allows the court to draw the reasonable inference that the 10 defendant is liable for the misconduct alleged.” Iqbal, 556 U.S. at 678. “In sum, for 11 a complaint to survive a motion to dismiss, the non-conclusory ‘factual content,’ and 12 reasonable inferences from that content, must be plausibly suggestive of a claim 13 entitling the plaintiff to relief.” Moss v. United States Secret Serv., 572 F.3d 962, 14 969 (9th Cir. 2009). 15 In deciding a Rule 12(b)(6) motion to dismiss, as with a Rule 12(b)(1) motion, 16 a court “accept[s] factual allegations in the complaint as true and construe[s] the 17 pleadings in the light most favorable to the nonmoving party.” Manzarek v. St. Paul 18 Fire & Marin Ins. Co., 519 F.3d 1025, 1031 (9th Cir. 2008). However, a court need 19 not “assume the truth of legal conclusions merely because they are cast in the form 20 of factual allegations.” Fayer v. Vaughn, 649 F.3d 1061, 1064 (9th Cir. 2011) (per 21 curiam) (internal quotation omitted). ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 10 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.995 Page 11 of 25 DISCUSSION 1 2 State Claims 3 The State Defendants assert that Plaintiffs’ state law claims, under the SEPA 4 and the OPMA, are barred from proceeding in federal court under the Eleventh 5 Amendment of the United States Constitution. ECF No. 24 at 2. 2 6 Plaintiffs respond that their state law claims may proceed in federal court 7 because they seek injunctive, not monetary, relief and because Plaintiffs’ federal and 8 state claims derive from a common nucleus of operative fact that “must be tried in 9 one judicial proceeding.” ECF No. 32 at 23. 10 Courts may exercise supplemental jurisdiction over state law claims “in any 11 civil action of which the district courts have original jurisdiction” and the state law 12 claims “are so related to claims within such original jurisdiction that they form part 13 of the same case or controversy under Article III of the United States Constitution.” 14 28 U.S.C. § 1367(a). However, the Eleventh Amendment provides that a state is 15 immune from suit unless it has waived its immunity or Congress has abrogated its 16 immunity through legislation. Va. Office for Prot. & Advocacy v. Stewart, 563 U.S. 17 247, 253 (2011). This grant of immunity encompasses state agencies. P. R. 18 Aqueduct & Sewer Auth. v. Metcalf, 506 U.S. 139, 144 (1993). “A state’s waiver of 19 20 21 The State Defendants’ Motion to Dismiss is filed at ECF No. 22, but their brief is filed at ECF No. 24 as a Praecipe. 2 ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 11 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.996 Page 12 of 25 1 Eleventh Amendment immunity and consent to suit must be ‘unequivocally 2 expressed.’” Doe v. Regents of the Univ. of Cal., 891 F.3d 1147, 1152−53 (9th Cir. 3 2018) (quoting Pennhurst State Sch. & Hosp. v. Halderman, 465 U.S. 89, 99 4 (1984)). 5 Under the Ex Parte Young exception to Eleventh Amendment immunity, a 6 party may seek prospective injunctive relief against an individual state officer in her 7 official capacity. Doe, 891 F.3d at 1153 (citing Agua Caliente Band of Cahuilla 8 Indians v. Hardin, 223 F.3d 1041, 1045 (9th Cir. 2000));. However, “the Young 9 exception does not apply when a suit seeks relief under state law, even if the plaintiff 10 names an individual state official rather than a state instrumentality as the 11 defendant.” Id. (citing Pennhurst, 465 U.S. at 117). 12 As set forth above, Plaintiffs seek a declaratory judgment against the State 13 Defendants as well as injunctive relief for alleged violations of both state and federal 14 law, specifically NEPA, SEPA, OPMA, and FACA. ECF No. 1 at 31−32. The State 15 Defendants do not dispute that Plaintiffs can pursue federal claims for prospective 16 relief against the Director of Ecology, to the extent that those federal claims are not 17 dismissed for other reasons. ECF No. 34 at 6; see Ex Parte Young, 209 U.S. 123 18 (1908). With respect to Plaintiffs’ state law claims, however, the State Defendants 19 argue that Plaintiffs do not offer authority to support their argument that there can be 20 pendent jurisdiction simply because the claims seek prospective injunctive relief and 21 ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 12 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.997 Page 13 of 25 1 share a common nucleus of fact with the federal claims when the State Defendants 2 are raising the shield of sovereign immunity. ECF No. 34 at 6. 3 Plaintiffs do not purport to offer any evidence of waiver. See ECF No. 32 at 4 23−26. Rather, Plaintiffs argue that this Court should reject Eleventh Amendment 5 immunity because Ecology, as “co-lead agency,” is an “indispensable party 6 necessary for this Court to render relief.” Id. at 25. This argument does not suffice 7 to clear the high hurdle set by the Eleventh Amendment, and the Young exception 8 does not apply to Plaintiffs’ state law claims. The State Defendants are immune 9 from state law claims pursuant to the Eleventh Amendment. Accordingly, the State 10 11 12 13 Defendants’ motion to dismiss the SEPA and OPMA claims is granted. Federal Claims NEPA Claims Plaintiffs claim NEPA violations based on the Integrated Plan and the 14 Kachess Pumping Plant. Plaintiffs assert, specifically, that Defendants’ FPEIS 15 violates NEPA, and SEPA, by: 16 17 18 19 20 21 a. Failing to identify, disclose and analyze reasonable alternatives in the EISs; b. Evaluating only one action alternative—the Yakima Plan—and the no-action alternative in the FPEIS, thereby foreclosing the possible selection of other reasonable and feasible alternatives; c. By pushing off project-specific environmental review and disclosure until after political decisions had been made and the Preferred Alternative had impermissibly ‘snow-balled’ and gained unstoppable momentum as evidenced by the alternatives evaluated in the EISs; ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 13 Case 1:19-cv-03155-RMP 1 2 3 4 ECF No. 43 filed 06/26/20 PageID.998 Page 14 of 25 d. By failing to identify, disclose and analyze potential, feasible mitigation measures in the EISs that could reduce the adverse impacts from the Yakima Plan; and e. By failing to properly consider and respond to public comments in the EISs. ECF No. 1 at 25−26. 5 NEPA does not provide an independent cause of action. ONRC Action 6 v. Bureau of Land Mgmt., 150 F.3d 1132, 1135 (9th Cir. 1998). Rather, Courts 7 review claims alleging NEPA violations under the Administrative Procedure 8 Act (“APA”), 5 U.S.C. § 706. Id. Courts must decide whether the defendant 9 agency “has considered all relevant factors and has explained its decision.” 10 Earth Island Inst. v. United States Forest Serv., 442 F.3d 1147, 1162 (9th Cir. 11 2006). 12 Before reaching the substance of Plaintiffs’ NEPA claims, the Court must 13 resolve the threshold jurisdictional issues raised by the Federal Defendants and 14 Intervenor Roza. First, Defendants and Intervenor dispute that Plaintiffs may 15 challenge Reclamation’s selection of the Integrated Plan after enactment of the 16 Dingell Act. Second, Defendants dispute on standing and ripeness grounds whether 17 this Court has jurisdiction over Plaintiffs’ challenges to the KDRPP. 18 Dingell Act 19 “Agency decisions that allegedly violated . . . NEPA are reviewed under the 20 APA.” Alliance for the Wild Rockies v. U.S. Forest Service, 907 F.3d 1105, 1112 21 (9th Cir. 2018). The APA forecloses judicial review of agency action to the extent ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 14 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.999 Page 15 of 25 1 that “statutes preclude judicial review” or “agency action is committed to agency 2 discretion by law.” 5 U.S.C. § 701(a). 3 The Federal Defendants and Intervenor Roza assert that this Court lacks 4 subject matter jurisdiction over Plaintiffs’ NEPA claims regarding the Integrated 5 Plan because Congress enacted the Dingell Act, which mandates implementation of 6 the Integrated Plan as a programmatic framework. ECF Nos. 23 at 27−28; 25 at 7 10−11. Therefore, Federal Defendants argue that they have no discretion that could 8 be challenged under the APA. Plaintiffs respond that the notion that an authorization 9 act such as the Dingell Act would overcome the protections of NEPA is “absurd” 10 and “contrary to what the Dingell Act actually provides.” ECF No. 32 at 8. 11 Plaintiffs contend that, instead, the Dingell Act mandates that all actions with respect 12 to the Integrated Plan comply with NEPA. Id. at 8−9. 13 The Dingell Act provides that Reclamation, in coordination with Washington 14 State and the Yakama Nation “shall identify and implement projects under the 15 Integrated Plan that are prepared to be commenced during the 10-year period 16 beginning on the date of this Act.” Pub. L. 116-9 § 8201. The Dingell Act further 17 requires that the “projects and activities identified by [Reclamation] for 18 implementation under the Integrated Plan shall be carried out . . . in accordance with 19 applicable laws, including” NEPA and the ESA. Id. 20 21 By the plain language of the Dingell Act, the Court finds that the Federal Defendants are correct in their assertion that Congress has “removed Reclamation’s ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 15 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.1000 Page 16 of 25 1 discretion to implement the Integrated Plan, thus precluding a NEPA challenge to 2 the Integrated Plan programmatic EIS.” ECF No. 35 at 4−5; see Pit River Tribe v. 3 U.S. Forest Service, 469 F.3d 768, 780−81 (9th Cir. 2006) (“NEPA’s EIS 4 requirements apply only to discretionary federal decisions.”). Moreover, 5 “environmental review is contemplated for the individual projects that make up the 6 Integrated Plan, not for the Integrated Plan as a whole.” ECF No. 35 at 4. Plaintiffs 7 have not shown that this Court may exercise judicial review under the APA. 8 Therefore, the Court grants the Federal Defendants’ and Intervenor Roza’s Motions 9 to Dismiss with respect to Plaintiffs’ NEPA challenge to the Integrated Planon the 10 11 12 basis of lack of jurisdiction. Standing and Ripeness Article III, section 2 of the Constitution extends the power of the federal 13 courts to only “Cases” and “Controversies.” U.S. Const., Art. III, sect. 2. “Those 14 two words confine ‘the business of federal courts to questions presented in an 15 adversary context and in a form historically viewed as capable of resolution through 16 the judicial process.’” Massachusetts v. EPA, 549 U.S. 497, 516 (2007) (quoting 17 Flast v. Cohen, 392 U.S. 83, 95 (1968)). 18 To establish standing to sue under Article III, “a plaintiff must demonstrate 19 ‘that it has suffered a concrete and particularized injury that is either actual or 20 imminent, that the injury is fairly traceable to the defendant, and that it is likely that 21 a favorable decision will redress that injury.’” Washington v. Trump, 847 F.3d 1151, ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 16 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.1001 Page 17 of 25 1 1159 (9th Cir. 2017) (quoting Massachusetts, 549 U.S. at 517)). While an injury 2 sufficient for constitutional standing must be concrete and particularized rather than 3 conjectural or hypothetical, “an allegation of future injury may suffice if the 4 threatened injury is certainly impending, or there is a substantial risk that the harm 5 will occur.” Susan B. Anthony List, 573 U.S. at 158 (internal quotations omitted). 6 “While standing is primarily concerned with who is a proper party to litigate a 7 particular matter, ripeness addresses when litigation may occur.” Lee v. Oregon, 8 107 F.3d 1382, 1387 (9th Cir. 1997). “[I]n many cases, ripeness coincides squarely 9 with standing’s injury in fact prong.” Thomas v. Anchorage Equal Rights Comm’n, 10 220 F.3d 1134, 1138 (9th Cir. 2000) (en banc). “A claim is not ripe for adjudication 11 if it rests upon ‘contingent future events that may not occur as anticipated, or indeed 12 may not occur at all.’” Texas v. United States, 523 U.S. 296, 300 (1998) (quoting 13 Thomas v. Union Carbide Agric. Products Co., 473 U.S. 568, 581 (1985) (internal 14 quotations omitted)). If a claim is not ripe for adjudication, the Court lacks subject 15 matter jurisdiction, and the claim must be dismissed. Southern Pacific Transp. Co. 16 v. City of Los Angeles, 922 F.2d 498, 502 (9th Cir. 1990), cert. denied, 502 U.S. 943 17 (1991); see also Fed. R. Civ. P. 12(h)(3) (requiring court to dismiss an action if, at 18 any point in the proceedings, the court determines it lacks subject matter 19 jurisdiction). 20 21 “Determining whether [an action] is ripe for judicial review requires [the Court] to evaluate (1) the fitness of the issues for judicial decision and (2) the ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 17 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.1002 Page 18 of 25 1 hardship to the parties of withholding court consideration.” Nat’l Park Hospitality 2 Ass’n v. DOI, 538 U.S. 803, 808 (2003). In the context of judicial review under the 3 APA, agency conduct is ripe for review only after final agency action. 5 U.S.C. § 4 704. 5 The Federal Defendants argue that Plaintiffs’ NEPA claims regarding the 6 KDRPP are not ripe because the Tier-1 EIS and the Tier-1 ROD are not final agency 7 actions, and, therefore, these claims will not be ripe until the Tier-2 EIS is complete. 8 See ECF No. 35 at 2 (“opportunity to challenge final agency actions will arise at a 9 later stage of the project when and if a pumping plant is authorized”). The Federal 10 Defendants maintain that Plaintiffs’ claim is analogous to the project challenged in 11 Rapid Transit Advocates, Inc. v. S. Cal. Rapid Transit Dist., 752 F.2d 373 (9th Cir. 12 1985), because it involves “tiered environmental review for a site-specific project, 13 rather than a programmatic challenge like those at issue in the cases Plaintiffs cite.” 14 ECF No. 35 at 7. The Federal Defendants advocate an outcome consistent with 15 Rapid Transit Advocates, in which the Ninth Circuit held that the plaintiffs’ NEPA 16 claim would not ripen until the second tier of the project was complete because, until 17 that time, the agency had not committed to funding construction and the plaintiffs 18 would not be affected until the decision was made. ECF No. 35 at 7; Rapid Transit 19 Advocates, 752 F.2d at 378−79. 20 21 Roza, in addition to arguing that Plaintiffs’ claims regarding the KDRPP DEIS, SDEIS, and Tier-1 EIS are unripe, argues that Plaintiffs do not allege ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 18 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.1003 Page 19 of 25 1 sufficient injury to support standing to challenge the Tier-1 EIS. ECF No. 23 at 32. 2 Roza argues that Plaintiffs allege injuries in the form of “visual blight from the 3 lowered level of Lake Kachess Reservoir, destruction of private and/or community 4 water wells, impairment of critical wildlife habitat used and enjoyed by Plaintiffs, 5 and diminishment of Plaintiffs’ property values.” Id. However, Roza continues, 6 these alleged injuries “would only occur in the event that Reclamation authorizes the 7 KDRPP,” and “neither the Integrated Plan, the 2013 ROD, nor the 2019 ROD 8 commit Reclamation to undertaking any site-specific action.” Id. 9 Plaintiffs respond that the FPEIS, the 2013 ROD and the 2019 Tier-1 EIS “all 10 . . . form the basis for [Reclamation’s] and DOE’s long-evolving Yakima Plan, 11 which, as alleged in the Complaint, pre-determined the future outcome by failing to 12 disclose and analyze viable alternatives and thus represents a concrete injury 13 justiciable now.” ECF No. 32 at 13. 14 “[E]nvironmental plaintiffs adequately allege injury in fact when they aver 15 that they use the affected area and are persons ‘for whom the aesthetic and 16 recreational values of the area will be lessened’ by the challenged activity.” Friends 17 of the Earth, Inc. v. Laidlaw Envtl. Servs., Inc., 528 U.S. 167, 183 (2000) (quoting 18 Sierra Club v. Morton, 405 U.S. 727, 735 (1972)). “Once a plaintiff has established 19 an injury in fact under NEPA, the causation and redressability requirements are 20 relaxed.” Cantrell v. City of Long Beach, 241 F.3d 674, 682 (9th Cir. 2001). 21 ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 19 Case 1:19-cv-03155-RMP 1 ECF No. 43 filed 06/26/20 PageID.1004 Page 20 of 25 The DEIS and SDEIS issued in this case were by their terms draft documents. 2 ECF Nos. 23-5; 1 at 19−20. While on first impression the Tier-1 ROD narrows the 3 scope of future action with respect to the KDRPP, viewing Plaintiffs’ allegations in 4 the light most favorable to Plaintiffs, there is nothing finalized, such as any decision 5 authorizing construction or even selecting a design. See ECF No. 25-4 at 167. “A 6 claim is not ripe for adjudication if it rests upon contingent future events that many 7 not occur as anticipated, or indeed may not occur at all.” Texas, 523 U.S. at 300. In 8 this case, there is nothing settled, and all of the alleged injuries would be contingent 9 on as-yet undetermined future decisions and events. Because Plaintiffs are not able 10 to adequately define any “certainly impending” activity by Defendants that likely 11 will injure Plaintiffs’ interests related to Lake Kachess Reservoir, the Court finds 12 that Plaintiffs have not presented a sufficiently concrete injury for purposes of 13 standing or ripeness. Susan B. Anthony List, 573 U.S. at 158. Without establishing 14 standing and ripeness, Plaintiffs have failed to establish federal subject matter 15 jurisdiction. Therefore, the Court grants Federal Defendants’ and Roza’s Motions to 16 Dismiss, on the basis of lack of jurisdiction, with respect to the remainder of 17 Plaintiffs’ NEPA claims. 18 ESA Claim 19 The Federal Defendants maintain that this Court lacks jurisdiction over 20 Plaintiffs’ ESA claims because Plaintiffs have not “complied with the sixty-day 21 notice requirement or the administrative exhaustion process.” ECF No. 35 at 2. The ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 20 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.1005 Page 21 of 25 1 Federal Defendants cite to Ninth Circuit caselaw demonstrating that “[t]he sixty-day 2 notice requirement is jurisdictional.” Klamath-Siskiyou Wildlands Ctr. v. 3 MacWhorter, 797 F.3d 645, 647 (9th Cir. 2015). Plaintiffs do not maintain that they 4 complied with this jurisdictional requirement. See ECF No. 32 at 35−36. Without 5 Plaintiffs’ having satisfied the sixty-day notice requirement, this Court does not have 6 jurisdiction over the ESA claims. Therefore, as Plaintiffs have not demonstrated that 7 there is a jurisdictional basis for their ESA claim to be before this Court, the Court 8 grants the Federal Defendants’ and Roza’s Motions to Dismiss the ESA claim for 9 lack of jurisdiction. 10 FACA Claim 11 Plaintiffs assert in their Complaint that all Defendants violated FACA through 12 their participation in the Yakima Workgroup, which Plaintiffs argue amounted to an 13 ad hoc advisory group that is impermissible under FACA. ECF No. 1 at 30. 14 The Federal Defendants seek dismissal of Plaintiffs’ FACA claims on the 15 assertion that the claims are time-barred and, therefore, fail to state a claim under 16 Fed. R. Civ. P. 12(b)(6). ECF No. 35 at 8. The Federal Defendants argue that the 17 relevant alleged final agency actions occurred outside of the six-year statute of 18 limitations of FACA, when the Yakima Workgroup was formed in 2009 or when the 19 Workgroup adopted the Integrated Plan in 2012. ECF No. 25 at 21. 20 21 Plaintiffs respond that their “FACA/APA claims are not time-barred because there has been no ‘final agency action’ since the Yakima Workgroup is ongoing and ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 21 Case 1:19-cv-03155-RMP ECF No. 43 filed 06/26/20 PageID.1006 Page 22 of 25 1 still providing advice and recommendations to the Federal Defendants regarding the 2 Yakima Plan in violation of FACA and the APA.” ECF No. 32 at 19. The Federal 3 Defendants reply that, alternatively, the lack of a final agency action, which 4 Plaintiffs themselves argue when they allege ongoing activity, defeats Plaintiffs’ 5 FACA claim. ECF No. 35 at 8. 6 The FACA statute contains neither a private right of action nor a statute of 7 limitations. See Judicial Watch v. United States DOC, 736 F. Supp. 2d 24, 30 8 (D.D.C. 2010) (“Because the FACA does not explicitly confer a private remedy, 9 see generally 5 U.S.C. app. 2, and because this fact alone is ‘determinative,’ the 10 court holds that the FACA does not provide plaintiff with a private right of 11 action.”). “The APA grants district courts jurisdiction to review final agency 12 actions for which there is no other remedy.” Id. For the APA, courts apply the 13 general statute of limitations for civil actions against the federal government at 28 14 U.S.C. § 2401(a). Wind River Mining Corp. v. United States, 946 F.2d 710, 15 712−14 (9th Cir. 1991). That statute provides that “every civil action commenced 16 against the United States shall be barred unless the complaint is filed within six 17 years after the right of action first accrues.” 28 U.S.C. § 2401(a). Under section 18 2401(a), a cause of action first accrues when the “person challenging the action can 19 institute and maintain a suit in court.” Trafalgar Capital Assoc. v. Cuomo, 159 20 F.3d 21, 34 (1st Cir. 1998). 21 ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 22 Case 1:19-cv-03155-RMP 1 ECF No. 43 filed 06/26/20 PageID.1007 Page 23 of 25 Plaintiffs argue that their FACA claims are not time-barred because there 2 has been no final agency action from which the statute of limitations must be tolled 3 “since the Yakima Workgroup is ongoing and still providing advice and 4 recommendations to the Federal Defendants regarding the Yakima Plan in 5 violation of FACA and the APA.” ECF No. 32 at 19. First, this position ignores 6 that the allegations in the Complaint regarding the Workgroup relate to 2009 and 7 2012, as the Federal Defendants and Intervenor Roza maintain. See ECF Nos. 1 at 8 17−18; 23 at 44−45; at 25 at 20−21. Moreover, and more critically, Plaintiffs’ 9 position reinforces why the Complaint that they filed is not viable. If Plaintiffs’ 10 FACA claim is timely because there has not yet been a final agency decision, then 11 Plaintiffs have not stated a claim upon which relief can be granted because it is 12 axiomatic that agency action must be final to be reviewable. See 5 U.S.C. § 704. 13 Given that Section 704’s finality requirement is jurisdictional, Plaintiffs 14 have not shown that this Court has jurisdiction to determine Plaintiffs’ FACA 15 claim, because the FACA claim does not challenge a final agency action. See 16 Havasupai Tribe v. Provencio, 876 F.3d 1242, 1248, n. 2 (9th Cir. 2017) (“Final 17 agency action is a jurisdictional requirement imposed by 5 U.S.C. § 704.” (internal 18 quotation omitted). Therefore, the Court concludes that it lacks jurisdiction over 19 Plaintiffs’ FACA claim. The Court grants the Federal Defendants’ and Intervenor 20 Roza’s Motions to Dismiss with respect to the FACA claim and dismisses the 21 FACA claim without prejudice for lack of jurisdiction. ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 23 Case 1:19-cv-03155-RMP filed 06/26/20 PageID.1008 Page 24 of 25 CONCLUSION 1 2 ECF No. 43 The Court grants Defendants’ Motions to Dismiss, ECF Nos. 22, 23, and 25, 3 and dismisses jurisdiction without prejudice Plaintiffs’ Complaint for lack of 4 subject matter. See Southern Pacific Transportation Co., 922 F.2d at 502; Fed. R. 5 Civ. P. 12(h)(3); see also Missouri ex rel. Koster v. Harris, 847 F.3d 646, 656 (9th 6 Cir.), cert. denied sub nom. Missouri ex rel. Hawley v. Becerra, 137 S. Ct. 2188 7 (2017) (“In general, dismissal for lack of subject matter jurisdiction is without 8 prejudice.”). However, the Court does not grant leave to amend the complaint, as 9 amendment would be futile in light of the ongoing nature of the administrative 10 process. See Cahill v. Liberty Mut. Ins. Co., 80 F.3d 336, 339 (9th Cir. 1996) 11 (holding that denial of leave to amend is not an abuse of discretion when 12 amendment is futile); Lak v. State Bar of Cal., No. SACV 18-2171-PSG (KK), 13 2019 U.S. Dist. LEXIS 29643, at *9 (C.D. Cal. Jan. 11, 2019) (dismissing without 14 prejudice and without leave to amend where court found that it lacked subject 15 matter jurisdiction). 16 Accordingly, IT IS HEREBY ORDERED: 17 1. Defendants Washington State Department of Ecology and its former 18 Director Maia Bellon’s Motion to Dismiss State Law Claims, ECF No. 22, 19 is GRANTED; 20 21 2. Intervenor Roza Irrigation District’s Motion to Dismiss, ECF No. 23, is GRANTED; ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 24 Case 1:19-cv-03155-RMP 1 ECF No. 43 filed 06/26/20 PageID.1009 Page 25 of 25 3. Defendants United States Department of the Interior, Bureau of 2 Reclamation and its Commissioner Brenda Burman’s Motion to Dismiss, 3 ECF No. 25, is GRANTED. 4 4. Plaintiffs’ claims are DISMISSED WITHOUT PREJUDICE, without 5 costs or fees for any party and WITHOUT LEAVE TO AMEND. As 6 these rulings dispose of the case, the District Court Clerk shall enter 7 judgment of dismissal without prejudice. 8 9 10 5. All upcoming hearings and deadlines in this matter are vacated, and all pending motions are denied as moot. IT IS SO ORDERED. The District Court Clerk is directed to enter this 11 Order, enter judgment of dismissal without prejudice as directed, provide copies to 12 counsel, and close the file in this case. 13 14 15 16 DATED June 26, 2020. s/ Rosanna Malouf Peterson ROSANNA MALOUF PETERSON United States District Judge 17 18 19 20 21 ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS ~ 25

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.